Tractor Fender Cost Reduction

Scope: To reduce the Fender cost by 10% over the present Product Cost

Tools: ProE, ANSYS, VAVE Process

Timelines: Within 180 days from the kick off date

Results: Product cost reduce by more than 15% from the present cost

At Vigrotek, we follow a very structured process for Value Engineering completely focusing on end Customer satisfaction.

Product User / End Customer voice capture is the main input for this program

The Engineers at Vigrotek have experience in the area of Design, Analysis and Supplier development for Prototypes

Value Addition

  • Use of emerging Hydro forming Technology for variable cross section for variable loads defined
  • Alternate High strength steel usage
  • Introduction of alternate process for increasing the section modulus
  • Additional stiffness introduction for eliminating the vibrations at lamp mounting area to reduce the lamp failures

Effort Taken

Total effort of 900 Hours which included

  • Design
  • VAVE Process definition
  • Analysis using ANSYS
  • Design improvement
  • Part availability coordination with suppliers
  • Testing coordination